6. Set up process of an OLite rental display
6.1 Set up of a floor mount OLite rental display
Set up process
1. Installation of the foot beams and OLite rental feet. See detailed procedure "Install the OLite rental feet", page 41.
2. Installation of the adjustable feet. Note that this is optional. See procedure "Install an adjustable foot", page 43 for detailed
installation instructions.
3. Build up the floor mount (base stand) OLite rental display as described in procedure "Build up a floor mounted OLite rental
display", page 50.
Warnin g: The maximum height of a base stand OLite rental display is 12 tiles high.
4. Installation of the required power box(es). See manual of the used power box for more information about installing the power
box(es).
5. Power cabling of the OLite rental display. See chapter "Power cabling of an OLite rental display", page 60.
6. Installation of the digitizer(s) and, if used, the fiberlink and/or AEC. Follow the installation guidelines in the manuals of these
products.
7. Data cabling of the OLite rental display. See chapter "Data cabling of an OLite rental display", page 61.
8. Installation of the control software for the OLite rental display. See installation procedure described in the manual of the control
software.
9. Energize the OLite rental display and start up the control software. For more information about showing content on the OLite
display see manual of the control software.