Installing
28 HP StorageWorks 2/8q Fibre Channel Switch Installation Guide
Installing and initially configuring the switch
Installing a 2/8q FC Switch involves the following steps, each of which is discussed in the
following sections:
■ Unpack the switch and verify carton contents, page 28
■ Mount the switch, page 29
■ Install SFP transceivers, page 34
■ Connect the cables, page 35
■ Configure the switch, page 36
Unpack the switch and verify carton contents
The 2/8q FC Switch is shipped with the components shown in Figure 5.
Figure 5: Switch carton contents
1 2/8q FC Switch
2 2/8q FC Switch Quick Start Installation Instructions (printed)
3 Power cable (approved for use in the United States)
4 Mounting adapter brackets
5 Screws for the mounting adapter brackets (6)
6 Rubber feet (4)
7 Small Form Factor Pluggable (SFP) transceivers (4)
1
3
2
7
6
4
5