Hardware options installation 42
7.
Install the cache module.
8. Install the storage controller, if not installed ("Storage controller option" on page 40).
9. Install the capacitor pack.
10. Route the cable. ("BBWC battery pack or FBWC capacitor pack cabling to an optional controller"
on page 51)
11. Install the access panel.
12. Install the server into the rack.
13. Power up the server (on page 16).
Battery-backed write cache battery pack option
CAUTION: To prevent a server malfunction or damage to the equipment, do not add or
remove the battery pack while an array capacity expansion, RAID level migration, or stripe
size migration is in progress.