![](https://pdfstore-manualsonline.prod.a.ki/pdfasset/1/0c/10c8b42c-8e54-4011-8191-861a3a60c4cd/10c8b42c-8e54-4011-8191-861a3a60c4cd-bgf.png)
Site prep team and tasks 15
Electrical Yes No Reference
9when completed
Are two AC outlets (on different lines) available for the proposed
equipment?
page 31
Does the input voltage correspond to equipment specifications? page 32
Are the input circuit breakers adequate for equipment loads? page 32
Does the input frequency correspond to equipment specifications? page 32
Are lightning arresters installed? page 39
Have all sources of electrical interference been corrected?
Air-Conditioning Yes No Reference
9 when completed
Can the temperature be maintained between 16° and 32°C? page 54
Can temperature changes be held to less that 10°C per hour? page 54
Can humidity level be maintained between 20% and 80%? page 54
Building Access and Security Yes No Reference
9 when completed
Is there access control to the computer room? page 59
Is there access control for the customer site? page 59
Will any stair-walkers, lifts, ramps, floor coverings, or ladders be
required to install the equipment?
Define: ____________________________________________
page 59
Will the equipment fit through all doors, corridors, and in lifts,
both in size and weight?
page 59
Does the building have a loading dock?
Maximum access height is _____m.
page 22