Site prep team and tasks 15
Electrical Yes No Reference
9when completed
Are two AC outlets (on different lines) available for the proposed
equipment?
page 31
Does the input voltage correspond to equipment specifications? page 32
Are the input circuit breakers adequate for equipment loads? page 32
Does the input frequency correspond to equipment specifications? page 32
Are lightning arresters installed? page 39
Have all sources of electrical interference been corrected? 
Air-Conditioning Yes No Reference
9 when completed
Can the temperature be maintained between 16° and 32°C? page 54
Can temperature changes be held to less that 10°C per hour? page 54
Can humidity level be maintained between 20% and 80%? page 54
Building Access and Security Yes No Reference
9 when completed
Is there access control to the computer room? page 59
Is there access control for the customer site? page 59
Will any stair-walkers, lifts, ramps, floor coverings, or ladders be
required to install the equipment?
Define: ____________________________________________
page 59
Will the equipment fit through all doors, corridors, and in lifts,
both in size and weight?
page 59
Does the building have a loading dock?
Maximum access height is _____m.
page 22