![](https://pdfstore-manualsonline.prod.a.ki/pdfasset/7/3a/73af1f76-b07c-4ff5-bfc3-051f63f3a272/73af1f76-b07c-4ff5-bfc3-051f63f3a272-bgb.png)
October 26, 2006
7014-083C
Page 11
CB1200-I Pellet Insert
Mark area of
floor to cut
Starter hole
Keep sharp edge of
metal floor away from
power cord
• The rebrick (refractory), glass doors, screen rails,
screen mesh and log grates can be removed from a
factory-built rebox in order to gain minimum insert
opening requirements.
• Any smoke shelves, shields and bafes may be
removed from a factory-built rebox if attached with
mechanical fasteners.
• The metal oor of the factory-built rebox may be
removed to facilitate the installation of the insert only
when a 1 inch (25mm) airspace is provided between
the insert and the oor of outer wrap.
• If the oor is made of thin metal, we recommend using
a Quarda-Fire oor protector, Part 811-070, which is
available through your dealer.
Figure 11.1. Measure and mark the metal
oor for cutting. With a drill, make a starter
hole in each corner.
Figure 11.2. Using a saws-all, cut out the
oor.
Figure 11.3. Place the insert into the fac-
tory-built rebox. Ensure that the power
cord can not be damaged by the sharp metal
edge. You may need to cut out a notch to
accommodate the cord.
H. Removing Metal Floor of Factory-Built
Firebox