SharkRack Enclosure Installation Guide
ID-00210-000 REV D, ECO2773 Page 6 of 46
Chapter 1 Site Preparation
Check Facility Provisions
Ensure that the following conditions are met:
• Floor is level and of sufficient strength to support the rack and your equipment. At
maximum gross weight, the floor must be able to support 1000 lb/in
2
.
• A qualified professional should complete site electrical power supply set-up. Ensure the
types of outlets are consistent with the type of plugs on the power devices to be used.
• Check with a qualified HVAC technician to make sure the environment will support the
heat load of the products being installed in the cabinet.
• Select a location for the cabinet that will allow adequate space for the door to open freely
and slide-mounted equipment to be extended.
• Check that the site can accommodate the cabinet footprint and mounting locations
according to the illustrations in Figure 3 and Figure 4.