A SERVICE OF

logo

3-4 HP Surestore FC 1Gb/2Gb Switch 16B Installation and Reference
Operating the HP Surestore FC 1Gb/2Gb Switch 16B
3
LEDs On the Power Supply Side
Figure 3-2 shows the power supply side of the switch with the LEDs identified.
Figure 3-2 The power supply side of the FC 16B
Steady green The port is transmitting/
receiving at 2 Gbps.
No action required.
Below
Serial
Port
Indicates
switch
power
No light Either the switch is off, or
boot is not complete, or
boot has failed.
Verify that the switch
is on and boot has had
time to complete. If
there is still no light,
contact your HP
account representative.
Steady green Switch is on and boot has
successfully completed.
No action required.
Slow-flashing
green
Diagnostic failure on one or
more ports.
Errors may be listed in
the error log. Refer to
the Fabric OS
Procedures Guide for
more information.
Table 3-1 SFP Media Side LED Patterns During Normal Operation
Location
of LED
Purpose
of LED
Color of LED Status of Hardware Recommended
Action
Switch Status LED
Power Supply LED (2x)
AC Power Switch (2x)
Power Supply #2
Spring Latch (2x)
Fan Tray Assembly (containing
Power Supply #1
fans #1 and 2)
Fan Tray Assembly
fans #3 and 4)
(containing