SpectraLink Corporation T1 Remote Module Installation
Link WTS – Link 3000 MCU
Do not install cards until power is connected.
4.3 Connect Power to Shelves
SpectraLink recommends that a licensed electrician install the –48V DC power supply
and connect power to the shelves.
See Link WTS – Link 3000 MCU: Installation, Connect Power to Shelves, for more
information.
4.4 Install Cards
The shelf diagram below shows a fully loaded Expansion Shelf. Any type of Interface
Module can be installed in slots 3-12.
Cards contain components that may be damaged by electrostatic discharge.
Before handling any of the cards, the installer must attach the grounding
strap (included in the Administration Kit) to his or her wrist, and attach the
other end of the strap to ground. Only handle the cards by their edges. Do
not touch connector contact areas, do not lift cards by any of the components,
and do not lay cards down on their component sides. When laying a card
down, place it component side up on top of the anti-static bag in which it was
shipped.
Install T1 Remote Module
1. Slide the T1 Remote Module into Slot 1 of the Expansion Shelf, until the card
clicks into place. Tighten the screws at the top and bottom of the card to secure it.
Install Expansion Shelf Controllers (CSC300)
2. Slide the Expansion Shelf Controller Card into Slot 2 of each shelf (2-20), until
the card clicks into place. Tighten the screws at the top and bottom of the card to
secure it.
3. Slide the Interface Modules into Slots 3-12 of each shelf (2-20) until the card
clicks into place.
Install Interface Modules (CPx316)
4. Slide the first Interface Module into Slot 3 of the Primary Shelf, until the card
clicks into place. Tighten the screws at the top and bottom of the card to secure it.
5. Slide additional Interface Modules into their slots. Slots can be left empty if
desired.
The following diagram shows a sample fully loaded Remote Expansion Shelf.
Part Number: 72-0059-06-E.doc Page 18