A SERVICE OF

logo

Effective 4/00
Page 19
IL 33-FX6-1
For Kits Supplied with a Breaker Mounted CPT
Only.
STEP 10: CONNECTING THE LINE SIDE HV
WIRES
NOTE: The power convention of the FP25 Break-
ers is normally Top to Bottom, meaning
the Top Breaker Stabs are on the Line
Side of the Breaker and the Bottom
Breaker Stabs are on the Load Side.
The HV Wires from the CPT MUST BE
ATTACHED to the Line Side of the
Breaker. If it is determined that the power
flow for the Breaker application is oppo-
site the normal convention, the HV Wires
must be attached to the bottom Stationary
Contact Assemblies. The bolts used to
connect the PT Wires in Step 9-D can be
used to connect the HV Wires.
A. Remove and save the Retaining Plate and
mounting hardware that secures the Phase 1 or
Phase 3 top Breaker Stab.
B. Remove and save the Phase 1 or Phase 3
Breaker Stab.
Fig. 40 Overview: Line Side HV Wires
Connected to the Top Breaker Stabs
C. Using drilling plan ā€œDā€, drill and tap the Phase
1 or Phase 3 Breaker Stab to accept a .250-20
bolt.
.22
.50
PHASE 1 COPPER CONDUCTOR SHOWN
REVERSE FOR PHASE 3 COPPER CONDUCTOR
DRILL AND TAP
FOR .250-20 (1)
Fig. 41 Drilling Plan ā€œDā€
Fig. 42 Drilled and Tapped Breaker Stab