IMPORTANT INITIAL INSTALLATION NOTES FOR STRATA DK8 AND DK16!
These minimum installation steps must be carried out for proper system operation.
I. Set the S WI switch in the Base Unit ON for BATTERY OPERATION; otherwise, allprogrammed
customer data will be lost on power down.
2. If required, install KSTU and K4RCU in the DK16 Base Unit, or QCDUs, QSTU, QCNU,
QRCU, and QSMU in the DK8 KSU.
3. If the DK16 system is configured with an Expansion Unit, follow the order prescribed
below:
a) Install PDKU, PEKU, PSTU, PESU, or KCDU in Slot 04 of DK16 Expansion Unit.
b) If installing two KCDUs in DK16, install a KCDU in Slot 05. The only PC9 allowed in
the Expansion Unit with a KCDU PC9 is a second KCDU PC9 (except for PIOU(S).
c) If the system is configured with a PCOU, install it in Slot 05 in DKI6. (The system
cannot be configured with both a PCOU and KCDU in the Expansion Unit.)
d) If the system DK16 is configured with a PIOU or PIOUS, install it in Slot 06. (Slot 07
should be reserved for future use.)
4. Initialize Programs 00 - 97 by running Program 90 for DK8 and DK16.
5. Run Program 92-1,2, 3,4,5, and 9 for DK8 and DK16.
6. For DK16 installation only, enter the hardware configuration with Program 03, exit the
programming mode, turn power OFF for five seconds, then turn power back ON.
Program 03 does not apply to DK8.
WHEN LATER ADDING DK16 KSU PCBs
1. Turn power off when installing PCBs, then turn power ON.
2. Install new PCBs and set the new configuration with Program 03. (Turn power OFF for
five seconds after running Program 03.)
3. Program new features, options, etc., created by new additions.
WHEN LATER ADDING DK8 KSU PCBs
1. Turn power off.
2. Install PCB(s).
3. Turn power on.
4. Program new features, options, etc., created by new additions.